Mt Isa Mine Copper Concentrator

Back to case studies

Improvement of copper plant recovery

The Mt Isa Mine (MIM) Copper Concentrator was first commissioned in 1973. Flotation plant capacity had progressively become constrained due to higher throughput, higher head grades, increased head grade variability, higher talk levels and the need to produce high grade concentrates.

The aim of the flotation capacity upgrade project was to improve copper plant recovery by approximately 2% through major brown fields work completed in two stages. This work included the installation of additional flotation equipment, pumps and pump boxes, lifting facilities, electrical supply, instrumentation, DCS upgrade, reagent distribution and process piping.

Ausenco’s scope included engineering design, procurement, project management and construction support for the following reconfigure flotation cleaner columns for parallel operation; install Jameson Pre flotation cleaner unit; install separate Jameson slag cleaner unit; install four 100m³ scavenger tank cells; install two 100m3 scavenger cleaner tank cells; reconfigure existing roughers to pre-flotation roughers; reconfigure existing scavenger units to rougher duty.

  • Designing and procuring large items of equipment that could be installed into the existing concentrator building
  • Designing for a large number of tie-ins located in an operating plant with restricted access and planning for minimal plant down time
  • Plant performance exceeding design parameters with minimal commissioning and ramp up issues
  • Incentives fully paid that included operational performance 6 months after PC

Project details

Offering
Concentrators
Commodity
Copper
Location
Australia
Business line
Minerals & Metals
Client
Mt Isa Limited
Timeframe
2001
Solution phase
Create (EPCM)