Butane Truck Offload and Storage

Back to case studies

Ausenco provided EPCM services for Phase I of a two-phase project for the Christina Lake 10,000 bbl/day pilot facility.

Services for Phase I included the butane load-in and storage facility, providing one truck offload riser and the three 30,000 USG storage bullets and injection pumps. Ausenco was also responsible for the interconnecting piping and tie-ins through the plant to the final butane injection points.

Project highlights:

  • butane truck load-in facility
  • mechanically complete after 20 days in the field
  • zero rework
  • 100% shop fabricated
  • utilised PlantAPPS™ for spool tracking during fabrication, installation, inspection and testing.

Project details

Commodity
Oil sands
Location
Conklin, Alberta
Business line
Oil & Gas, Power
Client
Cenovus Energy
Timeframe
June 2003 - December 2003
Services
Engineering, Construction management