Tulawaka gold project operating above capacity
- Brand:
- Ausenco
- Client:
- Barrick Gold
- Location:
- Tanzania
- Commenced:
- 2004
Design and construction of a 365 000 t/y gold processing plant including crushing, grinding, gravity CIL, intense cyanidation, desorption and gold room. Key infrastructure included TSF, water dams, village, water supply from local river and second-hand diesel power station.
Ausenco’s scope included feasibility study optimisation; engineering design; procurement; transport and logistics; constructions; and commissioning and performance testing.
• Project delivered under budget, on time and under difficult conditions
• Over two million man hours, local workforce of over 600, LTIFR 0
• Self managed civil works and installation of piping to reduce costs
• Gold plant is currently operating above capacity
View the full factsheet here.